On a commercial job the millwork usually arrives from a shop that is not on site, to be installed by a crew that did not build it. When something goes wrong, it is almost always at a boundary nobody wrote down: who took the field dimensions, who received the crates, who put the blocking in the wall. Those boundaries are cheap to settle before the award and expensive after it.
An installer can only price what is defined. Before the award, the bid set for the millwork package should include:
Each line below belongs to someone. The award is the moment to decide who, because every one of them becomes a change order or a backcharge when it is left open.
Casework installed in a space that is still wet or unheated moves after it is set. The installer's price assumes a conditioned space, walls and floors within the tolerance the shop drawings allow, and a place to store crates before they go up.
If the schedule has millwork arriving before the space is conditioned, that is a decision to make at award, with the storage and acclimation it requires carried in somebody's number.
Fabrication lead time usually starts from approved shop drawings. Field dimensions should feed into those drawings, which means the openings have to exist and be measurable before the shop releases the cut. Confirm the order of events before award:
Ask how damage found at delivery is recorded, how punch items are tracked by room, and what the closeout includes: photos, attic stock, hardware keys and the fabricator's warranty. A record kept from the first crate is what keeps a freight claim open to you instead of turning into a backcharge argument at the end.