Allowances are useful when a selection genuinely is not made yet. They are dangerous on finish carpentry, because the thing that changes with the selection is not only the price per foot. It is the installation method, the waste factor, the lead time and often the number of trips.
Carrying an allowance says the selection is open. It does not say the risk is gone. Someone still absorbs the difference between what was carried and what gets chosen, and on finish work that gap opens in more than one direction at once.
The estimator who writes the allowance and the crew who installs against it are usually looking at two different numbers by the time the selection lands.
A paint grade poplar base and a stain grade white oak base can be close in material cost and nowhere near each other in labor. Stain grade means joints have to be tighter, material selection matters, damage is not filled and sanded, and rework is not an option in the same way.
The same is true across the package. A flat stock casing and a profiled casing with a mitered head are different installs. A five inch base and a nine inch base behave differently against an out of plumb wall.
The most expensive consequence of an open selection is rarely the material. It is that the decision arrives after the crew has left the building, so the work splits into two visits: everything that could go in, then everything that waited.
Two visits to the same floor is not two half days. It is setup, protection, distribution and punch, run twice. When an allowance is written without a decision date attached, that outcome is the default.
The fix is not to refuse allowances. It is to bound them, so the number means something specific and the estimator and the subcontractor are describing the same job.
When those five lines exist, a late selection is a conversation about a number. When they do not, it is a conversation about who eats the cost, held in month five with a schedule already tight.
Defining the allowance does not slow the bid down. It is the difference between a price that survives buyout and one that starts unraveling the week the finish schedule is issued.