Two bids on identical drawings can be structured so differently that comparing the totals tells you almost nothing. Labor only and supply and install move material risk, waste, lead time and damage between the GC and the subcontractor, and each arrangement fails in a different place.
A labor only number and a supply and install number are answering different questions. One is the cost of putting the material up. The other is the cost of having the material be right, on site, on time, and replaced when it is not.
Leveling them as if they were the same line is how a buyout produces a saving that disappears by month two.
When the GC supplies material, several risks move with it, and they are rarely priced anywhere.
A supply and install number carries all of that, so it should be higher. The sub is pricing the risk of reordering, the buffer for waste, and the carrying cost of getting material to site early enough to acclimate.
What the GC buys with that premium is a single point of responsibility. When a piece is wrong, there is no meeting about whose material it was. The crew replaces it and the schedule holds.
Labor only works when the GC has real purchasing leverage, when the material is standard and locally available, and when someone on the GC's team owns quantity and delivery as an actual assignment rather than an afterthought.
Supply and install works when the material is specialty or long lead, when the schedule is tight enough that a reorder would be fatal, and when nobody on the GC side has the time to chase a lumber order through a finish schedule.
Whichever structure you choose, the same handful of items decide whether it holds up in the field.