Splitting scope across specialists is the default for good reasons. But every boundary between two subcontractors is a place where a schedule can stall and a responsibility can go missing, and on projects with several related carpentry scopes those boundaries are the ones that cost the most.
Three separate awards produce three competitive numbers, and the arithmetic is easy to defend at buyout. What is harder to see at that stage is the coordination cost, because it does not appear on any bid form. It appears later, in your own team's hours.
Every boundary needs a meeting, a sequence agreement and someone to arbitrate when the two sides disagree about a condition. That someone is your superintendent, and their time is the most expensive hour on the job.
The failure points are consistent across projects, and they cluster in the same handful of places.
One contract across related scopes does not just reduce paperwork. It moves the coordination inside the subcontractor, where it costs them rather than you, and it removes the argument about whose condition caused a problem because there is only one party.
It also produces one schedule instead of three that have to be reconciled, and one point of contact who can answer for the whole sequence rather than for a slice of it.
Consolidation is not always the answer, and pretending otherwise would be selling rather than advising. Split the scope when the trades are genuinely unrelated, when one scope is large enough that a specialist has a real cost advantage, or when a single sub does not have the capacity to hold all of it without stretching.
The question is not whether one sub is better than three. It is whether the boundaries you are creating sit in places where things break.
Combining scope only works if the sub can actually carry it. The questions are practical and the answers should be specific.